Current Status


NameMAD NameEPICS PVCamera TypeLensPosition 1Position 2Position 3Position 4Position 5
PMONPROF:LI20:45PROF:LI20:45Manta 125Computar 55Phosphor



SYAGPROF:LI20:2432CAMR:LI20:100Manta 125Nikkor 105YAG w/ITOPhosphor


USTHzOTRS:LI20:3070CAMR:LI20:101Mako 125Nikkor 105YAGTi discTi foilTi foil
USOTROTRS:LI20:3158CAMR:LI20:102Mako 125Nikkor 60YAGTi discTi foilTi foilTi foil
IPOTR1OTRS:LI20:3180CAMR:LI20:103Manta 125Tokina 100Ti disc



DSOTROTRS:LI20:3206CAMR:LI20:104Manta 125Nikkor 105Ti flatYAG


WDSOTROTRS:LI20:3230CAMR:LI20:105Manta 95Tokina 100Ti flat



DTOTR2
CAMR:LI20:106Manta 125Computar 55YAGTi flat


LFOV
CAMR:LI20:107Manta 125Nikkor 50DRZ



PRDMPPROF:LI20:3475CAMR:LI20:108Manta 95Nikkor 35-70Phosphor



Camera Notes

USTHz

USTHz checked out but there is an issue with not having mechanical limit switches. Soft limits need to be used instead and checked before moving. For the short term, best to ask an expert to verify it is set up properly (C. Clarke, J. Allen, S. Gessner). Negative motion is okay when watching with the camera but real caution needs to be used with positive motion.

USOTR

USOTR currently way zoomed out. Acting as "light detector".

IPOTR1

LED light is set up on the IPOTR channel accessible on the profile monitor EDM panel but the blue LED doesn't illuminate the target very well and will be improved.

DTOTR2

User control only please... This is on MC01 Ch7 (X) and Ch8 (Y). DTOTR_x: Position 0 is out and 98 is in. DTOTR_y: 108 is YAG. CAMR:LI20:105.

LFOV

User control only please... This is on MC01 Ch6. Position >100 is out and 0 is in.  CAMR:LI20:107. ND 2.00 filter is on a flipper controlled by the Beckhoff Digital IO, channel 21, output 1 (Binary 5V Out) -  APC:LI20:EX02:5VOUT_1. Value "ON" = filter in.

PRDMP (not a user area item but included for completeness)

This is a fixed phosphor screen, no mover. CAMR:LI20:108.

Oven Table Mover

Fully checked out. Left with the bypass line in the beam path.


Work in Progress

Toroids

Tunnel work complete- toroids are connected to long haul cables. Need to be brought online and calibrated. 

IP Wirescanner 1

Checked out motion controls. PMT3350 and PMT3360 appear offline but are connected to long-hauls and no signs of why there would be issues from the tunnel side (works now that triggers reconnected?). Work still needed here. See Fig 6 of this paper for a photo of the wirescanner card: https://slac.stanford.edu/pubs/slacpubs/16250/slac-pub-16410.pdf

IP Wirescanner 3

Checked out motion controls but LVDT is not calibrated. For an unobstructed position, 20 mm appears to be an okay on motor, 28 mm on LVDT. But it actually looks to me from the drawings that it ought to be about 90 mm. PMT3350 and PMT3360 appear offline but are connected to long-hauls and no signs of why there would be issues from the tunnel side. Work still needed here. 

Note, images of the card can be found here: https://drive.google.com/file/d/1scVopR61fpoo_dhtIH5aFozV2wHd0yiM/view?usp=sharing

IPOTR2 and IPOTR1P

Motion control is all good. Cables are prepared for the cameras. Just don't have cameras on these yet as they are not needed and we don't want to irradiate cameras without reason. IPOTR2 is controlled on OTRS:LI20:3202 and IPOTR1P is on OTRS:LI20:3175.

  • No labels