Notes May 2021:

5/26/2021:

  • KK: requests to organize PEER Review for PCIe TPR for the week of June 7th 2021 and completion of tasks for 5/7/2021 (15 working days after)
  • Matt W:

  1)  Matt Gibbs asked me about rate changes and how to incorporate with the "master beam controller".  In the end, we realized that he needs to communicate with Patrick about this.  We'll eventually know what to do once the whole mode/pattern/rate operation procedure is worked out.

  2)  The timing fiber distribution network for LCLS-II is complete!  A little hard to believe given our fanout shortage.  We borrowed heavily from other projects and reduced our flexibility until the next fanout fabrication run is done.

  3)  The B15 LLRF test stand now has a master source and synchronized TPG.  They have no TPG IOC running, though. At some point, they may want a copy running there.


  • No labels