DAQ installation

  • Jeff Tice will organize moving DAQ to IR2 (will use scissor jacks)
    • 14 COBS and a single RTM (borrowed from Owen)
  • Target date is Friday
    • Real RTMs are 1.5-2 weeks away
  • Need 10G fibers between DAQ and Diagnostic Cluster 
  • We need power cables
    • Stuart will order cables and get delivery estimate after meeting
  • Power: 9x308v under the floor. 
    • 4 are attached to the rack PDUs
    • 2 are attached to cooling door
  • DAQ has two active power supplies, and 2 "hot" spares 
    • Might need outage to redistribute power

Firmware installation

  • FPGA can store 4 versions of firmware
    • One boots by default (Slot 0)
    • Possible to boot any of the 4
  • We are currently not using the most recent version of firnware (5-7 version behind) 
    • Science rafts are at Step 0

    • Corner raft(s) already at Step 2.

  • Available (or soon to be available) firmware releases:
    • Step 1
      • Possible to update SCI to support PGP firmware load, without changing REB firmware
      • No changes to firmware except to add PGP firmware load
    • Step 2:
      • Changes reset behavior, get rid of automatic reset after loosing link (version 335)
      • (Global and SCI resets are independent) 
    • Step 3
      • Multiple mains, and synchronous step, primitive (nonusable LAM) 
      • This will require CCS update to support
    • Step 4
      • Look at me (not implemented on DAQ side), multiple sequencers
      • CCS will need update to support multiple sequencers (on branch).
      • Should be backwards compatible if only use one sequencer
    • Step 5
      • id register fix (not yet available)
      • DAQ fixes: Configuring transeivers (more reliable link)
      • OTM Redundancy (temporary bad things may happen if you power both halves of OTM)
  • Notes:
    • DAQ 2.5 will work with all existing firmware

    • This would be sufficient for 9 raft running and would allow multiple image clients 

    • DAQ 2.5.x will require Step 4 or 5

Plan

 