Item/Task | Sub-item/task | Owner | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | done | |||
fabrication | done | |||
loading | 9/3 | Received 8/29 | ||
testing 2 boards | 9/12 | |||
rest of FE boards fab and loaded | 9/19 | |||
all FE boards tested | 9/26 | |||
L4-6 Half-module production | Tim/Omar | |||
apv25 loading | done | |||
hybrid & sensor QA | done | |||
half-module production incl. QA | 9/5 | two modules to go on 9/2 | ||
L1-3 Module assembly | Tim/Sho | |||
Modules for detector | 9/12 | |||
Spares | 9/12 | |||
L4-6 Module assembly | Tim/Sho | |||
Modules for detector | 9/19 | |||
Spares | 9/19 | |||
FEB support | Richard | |||
Machine slots in support box | done | |||
Design pockets (need final FE board) | 9/12 | |||
Fabrication and dry assembly | 9/26 | |||
Mechanical dry run assembly | Who? | |||
w/o cabling and real FEBs (but FEB cold plate) | 9/5 | first stage mech progressing well | ||
Motion control system check | Takashi/John | |||
Test stages on vac box | 9/5 | Work with Matt on details | ||
Connect bottom U channel, set limits, calibrate | 9/12 | |||
Connect top U channel, set limits, calibrate | 9/12 | |||
Survey | Tim/Sho | overview and procedures needed | ||
L1-3 module survey | 9/19 | |||
L4-6 module survey | 919 | |||
U-channels survey | 9/26 | Need mounted modules (see below). | ||
SVT full assembly survey | Do after final assembly and checkout | |||
Internal cabling | Tim/Dave | Critical Path–Push Hard | ||
Magnet wire signal transmission test | done | |||
Magnet wire high voltage test | done | |||
FEB mezzanine card layout | done | |||
FEB mezzanine card fabrication | 9/12 | |||
Hybrid mezzanine card layout | done | |||
Hybrid mezzanine card fabrication | 9/12 | |||
L1-3 cross-over board design | 9/5 | |||
L1-3 cross-over board layout | 9/12 | |||
L1-3 cross-over board fabrication & assembly/checkout | 9/19 | Push for 3 day turnaround. | ||
LV mezzanine card layout | 9/5 | |||
LV mezzanine card fabrication | 9/12 | |||
HV mezzanine card layout | done | |||
HV mezzanine card fabrication | done | |||
Cable to LV (patch to FEB) | 9/19 | Ben to get quote on connect SOON | ||
Cable to HV (patch to FEB) | 9/19 | |||
prototype hybrid-FEB bundle assembly | 9/19 | Needs cards back and FEB | ||
prototype cross over-FEB bundle assembly | 9/26 | Needs cross over board | ||
prototype bundle tests with FEB | 9/26 | |||
production bundle assembly and test | 10/6 | critical path for full assembly (see below) | ||
FEB power bundle design (flange/patch) | done | |||
FEB power bundle assembly (flange/patch) | 9/5 | Need cable length estimate. 2 days of shop work. | ||
FEB high voltage bundle design (flange/patch) | done | |||
FEB high voltage bundle assembly (flange/patch) | 9/5 | Need cable length estimate. 2 days of shop work. | ||
FEB data cable design (flange/FEB) | done | |||
FEB data bundle assembly (flange/FEB) | 9/5 | |||
External cabling & Power | pelle | |||
High voltage | 9/12 | 2/3 bundles done. Waiting for more wire. | ||
Low voltage | 9/19 | mod needed to present bundle | ||
Fibers | Done. | Between flange and DAQ crate. | ||
PS checkout | Done. | |||
PS epics control | 10/6 | Can control through backup interface until ready. | ||
Power flange | Pelle | |||
Flange w/ board assembly | done | One spare included. | ||
Testing with FEB and PS | 9/12 | Need dummy connector on power. High voltage with banana plugs? | ||
Signal flange | Pelle | |||
Board fabrication (5 boards) | Done. | |||
Board prepping | Done. | |||
Board testing | Done. | Needs Ben for high-speed tests. | ||
Flange w/ board assembly | done | |||
Board fabrication (spares) | 9/26 | Spares, no rush. | ||
Board loading (spares) | 10/3 | ditto | ||
Board testing (spares) | 10/10 | ditto | ||
Chiller and cooling system | Marco | 9/12 | ||
Target | Clive/Marco | |||
Design | 9/5 | |||
Fabrication | 9/19 | |||
Testing | 9/26 | |||
Wire frame holder | Clive/Marco/Takashi | |||
Design | done | |||
Fabrication | 9/12 | Wire Stretching | ||
Testing | 9/12 | |||
Final SVT Assembly | ||||
Mount modules in U-channels and survey | 9/26 | See survey above | ||
Dress modules in U-channels with cabling | 10/10 | Use cables and cards completed 10/6 | ||
Assemble FEBs on cooling plate and dress with cables | 10/10 | cables are ready 10/6 Need 11 days? | ||
Full SVT assembly and cabling | 10/17 | Ready for full system testing | ||
ATCA/RCE Platform hardware | Ryan/Pelle | |||
RTM layout | done | After testing trigger interface at JLab. | ||
RTM fabrication & loading | done | |||
RTM checkout | 9/12 | |||
SVT DAQ commissioning | Ryan/Ben | |||
Commissioning of RCE platform with multiple FEBs and hybrids | 9/19 | Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly. | ||
Commissioning/testing of full RCE platform | 10/13 | Use all final hardware with increasing number of FEBs/modules. | ||
Shipping | Pelle/Matt/Bob | |||
SVT Box Design | 9/5 | |||
Procurement/fabrication SVT Boxes | Bob | 10/5 | ||
Assemble SVT Boxes | Bob | 10/12 | ||
Design Spares Boxes | 9/12 | |||
Order standard boxes | Marco | 9/26 | ||
Pack Boxes | ||||
Ship boxes |