Item/Task | Sub-item/task | Owner | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | Done 8/4 | |||
fabrication | 8/6-8/12 | |||
loading | 8/13-8/20 | |||
testing | 8/21- | |||
L4-6 Half-module production | Tim | |||
apv25 loading | 8/7 | |||
hybrid & sensor QA | 8/12 | |||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | ||
L1-3 Module assembly | Tim | 8/18-8/29 | ||
Modules for detector | 8/18-8/29 | |||
Spares | 9/1-9/5 | |||
L4-6 Module assembly | Tim | 8/18-8/29 | ||
Modules for detector | 8/18-8/29 | |||
Spares | 9/1-9/5 | |||
FEB support | Shawn | |||
Machine slots in support box | 8/8 | |||
Design pockets | 8/21-8/29 | Need loaded FEB for design | ||
Fabrication and dry assembly | 9/1-9/5 | |||
Mechanical dry run assembly | ||||
w/o cabling and real FEBs (but FEB cold plate) | 8/8 | |||
Motion control system check | Takashi | 8/15 | ||
Survey | overview and procedures needed | |||
L1-3 module survey | 9/1-9/5 | |||
L4-6 module survey | 9/8-9/12 | |||
U-channels survey | 9/8-9/12 | Need mounted modules (see below). | ||
SVT full assembly survey | 9/22-9/26 | |||
Internal cabling | Tim/Dave | |||
Magnet wire signal transmission test | done | |||
Magnet wire high voltage test | 8/8 | Pelle will do it. | ||
FEB mezzanine card layout | 8/8 | |||
FEB mezzanine card fabrication | 8/15 | |||
Hybrid mezzanine card layout | 8/13 | |||
Hybrid mezzanine card fabrication | 8/20 | |||
pre-production bundle assembly | 8/21-8/26 | |||
pre-production bundle test with FEB | 8/27-9/3 | |||
production bundle assembly | 9/4-9/12 | |||
FEB power bundle design | done | |||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | ||
FEB high voltage bundle design | done | |||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | ||
External cabling & Power | pelle | |||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | ||
Low voltage | Done. | |||
Fibers | Done. | Between flange and DAQ crate. | ||
PS checkout | Done. | |||
PS epics control | 9/1 | Can control through backup interface until ready. | ||
Power flange | Pelle | |||
Flange w/ board assembly | 8/8 | One spare included. | ||
Testing with FEB and PS | 8/8 | Need dummy connector on power. High voltage with banana plugs? | ||
Signal flange | Pelle | |||
Board fabrication (5 boards) | Done. | |||
Board prepping | 5/8-8/8 | |||
Board testing | 8/18-8/19 | Needs Ben for high-speed tests. | ||
Flange w/ board assembly | 8/20-8/27 | Potting. | ||
Board fabrication (spares) | 8/20-8/27 | |||
Board loading (spares) | 8/28-9/4 | |||
Board testing (spares) | 9/5-9/6 | Needs Ben for high-speed tests | ||
Chiller and cooling system | Marco | |||
ATCA/RCE Platform hardware | Ryan/Pelle | |||
RTM layout | 8/15 | After testing trigger interface at JLab. | ||
RTM fabrication & loading | 8/18-9/1 | |||
RTM checkout | 9/2-9/5 | |||
Target | Clive/Marco | |||
Design | 8/6-8/15 | |||
Fabrication | 8/18-8/22 | |||
Testing | 8/25-8/26 | |||
Wire frame holder | Clive/Marco/Takashi | |||
Design | 8/6-8/15 | |||
Fabrication | 8/18-8/22 | |||
Testing | 8/25-8/26 | |||
Mechanical dry run assembly | Shawn | |||
U-supports, FEB cold plate, stages | 8/8 | |||
Define cable lengths for power and HV bundles | 8/8 | |||
Mechanical assembly | ||||
Mount modules in U-channels | 9/1-9/5 | |||
Assemble FEBs on cooling plate | 9/15-9/19 | |||
Full SVT assembly assembly U-supports w/ modules stages | 9/15-9/19 | |||
Shipping | Pelle/Matt | |||
Box design | 8/12 | Nr of boxes, isolator requirements for transport of delicate modules | ||
Procurement/fabrication | 9/12 | |||
Assembly | 9/19 |