Item/Task | Owner | sub-item/task | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | Done 8/4 | |||
fabrication | 8/6-8/12 | |||
loading | 8/13-8/20 | |||
testing | 8/21- | |||
L4-6 Half-module production | Tim | |||
apv25 loading | 8/7 | |||
hybrid & sensor QA | 8/12 | |||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | ||
L1-3 Module assembly | Tim | |||
L4-6 Module assembly | Tim | |||
Mechanical dry run assembly | Shawn | |||
w/o cabling and real FEBs (but cold plate) | 8/8 | |||
Motion control system check | Takashi | 8/15 | ||
Survey | Tim/Takashi/John | overview and procedures needed | ||
Modules | ||||
U-channels | ||||
SVT full assembly survey | ||||
Internal cabling | Tim/Dave | |||
FEB mezzanine card layout | 8/8 | |||
FEB mezzanine card fabrication | 8/15 | |||
Hybrid mezzanine card layout | 8/13 | |||
Hybrid mezzanine card fabrication | 8/20 | |||
pre-production bundle assembly | 8/21-8/26 | |||
pre-production bundle test with FEB | 8/27-9/3 | |||
production bundle assembly | 9/4-9/12 | |||
FEB power bundle design | done | |||
FEB power bundle fabrication | Need cable length estimate | |||
External cabling & Power | Pelle | |||
High voltage | ||||
12. target--design, fab, check 13. wires--design, fab, check 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes