Information provided to Graham Heyes and Dennis Weygand

  • period: February 2014 to the end of April 2014
  • processing: 0.6 million CPU hours
  • data storage and distribution: 13 TB of tape storage needed and most of this is to be exported too

(Note: known only to within a factor of 2)

==> ~280 slots needed constantly for three months

             ==> ~18 Ivy Bridge nodes (16 core systems)

No complaints.