Reason for change
This release features the full statistics (55 days) version of the rate normalizations for the Pass7 era. There's also a few more minor changes detailed in the release notes below.
Test Procedure
We have processed LPA runs in the DEV pipeline with this version of L1Proc.
Rollback procedure
We can easily switch back to the previous version of L1Proc before the FSSC switches over to the new photon database (we probably have a few hours to rollback, if needed). This would have to be coordinated with ASP.
CCB Jira
Details
DigiReconCalMeritCfg-01-20-02
- Update normalized rates for Pass7 with 56 days up to September 25th 2011.