LSSTCAM charge numbers:16714-B2121, 10139-B2019
Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
eTraveler standards, conventions, best practices documentation. All Camera subsystems must use | 5/16/15 | Mark/Robert |
|
eTraveler procedure for mechanical assembly of raft electronics boards (attach coldbars and FPGA heat sink) | Done 5/4/16 | Robert | |
eTraveler procedure for raft electronics board initial testing (bring up board and load firmware. Prep for TS-REB testing) | Complete 5/23 | Robert | |
eTraveler procedure for posting RGA results | Complete TBD | Mark/Robert | Coordination with Mark Bostic at SLAC for posting RGA |
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
Write demo eTraveler procedures to show Walt Innes how eTraveler can be used to monitor and control auxiliary electronics inventory | Done 4/20/16 | Robert | |
With Walt Innes, plan assembly sequence and eTraveler procedures for ~500 commercial auxiliary electronics parts | Complete TBD | Robert | |
Write eTraveler procedures for inventory control of commercial auxiliary electronics parts | 6/15 | Mark/Robert | |
Write eTraveler procedures for testing of auxiliary electronics assemblies as needed (e.g. Camera protection system) | Complete TBD | Robert | |
Consult with SLAC Camera subsystems (Cryo, CBM, Shutter, I&T) on assembly sequences, scope and "load balancing" for writing eTraveler procedures | 6/15 | Mark/Robert | |
Plan for Camera operations & maintenance documentation, relationship to eTraveler | 7/15 | Mark/Robert |
|
Deliverable | Complete Date | Responsible |
---|---|---|
3 monthly reports | Monthly 15th, 31st | Robert |
Camera subsystem FDR, MRR site and document prep | Roughly monthly | Mark |
Camera document control: doc mgmt, prep, routing, release | (As needed, currently 4-10 hours per week) | Mark |
Charge numbers:13877-T2101
Deliverable | Complete Date | Responsible | Blockers/Issues |
---|---|---|---|
Finish release of 0266 ICD | 4/27 | Mark |
|
Finish release of Platform ICD | 4/20 | Mark |
|
Finish release of Timing ICD | 5/4 | Mark |
|
Finish release of HPS FRSs | 5/11 | Mark |
|
Finish release of HPS ESDs | 5/11 | Mark |
|
Charge numbers:
Deliverable | Complete Date | Responsible | Blockers/issues |
---|---|---|---|
ePix100A detector data sheet | 5/13 | Mark | |
ePix100A installation guide | 5/13 | Mark | |
ePix100A detector ops/api guide | 5/13 | Mark |
|
Most of these are wish listy items with no time or budget.
Deliverable | Complete Date | Responsible | Blockers/issues |
---|---|---|---|
Summer intern - AIR Elx software library API docs, consider Doxygen | |||
Review permissions scheme for ppareg Confluence space | Mark | ||
Reorg and new navigation scheme for ppareg Confluence spaec | Mark | ||
Run interference with LCLS, LCLS-II doc control and CDR/PDR/FDR and CD* review prep. | Mark |