You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 36 Next »

SVT EPICS Power Instructions

DAQ & Power Mapping in Group C

Operation

!!! Remember to make sure the detector is being cooled. !!!

!!! Remember to make sure the interlocks are in the state you want them. !!!

Logbook

1/14/2013

System status (from Ben's email Jan 7th):
We can currently power 8 FEBS.  We can power every hybrid attached to those 8 FEBS: 30 Hybrids.  All Hybrids that we can power are able to sync, except for FEB 8, Hybrid 2, which has just 1 APV that won’t sync.
Link to excel file. 

L1t (DAQ FEB #0 and GUI FEB #0) has what looks like a short on the output side of the regulator on DVDD (we can’t see the short probing the pins from outside).
L6b (DAQ FEB #5 and GUI FEB #7) first appeared to have a short on DVDD. After 5mins and a power cycle it came back with current levels that looked reasonable except that the DVDD level indicated it had no control link. 

10:00AM
Danh Du finished terminating the pigtails from the flange boards. We are missing a single female pin on one REDEL connector. Its wire was cut and folded back waiting for new pins. He did not test the pinout at this point.

11:00AM
Removing FEB cooling plate from SVT box to rework FEBs.

12:54PM
Extracted thee FEB cold plate and removed all FEBs. The two non-working FEBs (L1t and L6b) were sent to Ben directly; the other were given to Lupe for rework.
The default rework is to add Zener diodes to all FEBs and also to remove the FPGA LED that is always on (it's on the cooling plate side so we can't see it anyway; it indicates FPGA programming OK).
I added the serial number of each board to the mapping on the DAQ & Power Mapping in Group C page.

4.00pm
Found that P5 connector had DIG_GND swapped across the flange. The two pigtail connector seemed ok (the twisted pair went into adjacent pins as expected) which leaves the only (question) possibility of having a swap at the pads on either side of the flange board.
=>Danh Du corrected this on the air side P5 connector.

5.15pm
Placed FEB L1t on cold plate next to the SVT box and connected P1 power cable. Without detector attached the FEB powers up fine with expected currents. When connecting the L1t detectors we see again a 3A current on DIG as before. We also tried connecting L1-3 spare half-modules with the same result. We then swapped out P1 with P5 and powered the FEB as if it was L1b. This was successful. Thus the problem points to some problem in the L1t power cable. Tomorrow we need to ohm out that path to see if we can find a problem.

6:30 p.m.
L1t, L6t and L6b modules have been tested with the single-FEB setup. All OK.

1/15/2015

11:00am
Ohming out the L1t power connection revealed a short on the long cable between the breakout boxes between DIG power and the metallic braid. This together with the fact that the SVT box, and therefore hybrid grounds, was not isolated from the optical table most likely caused a current path from the braid to the breakout box and onto the detector. This is why connecting the FEB to hybrids made the difference; it is otherwise isolated from the SVT box. 
The long cable (P1) is being reworked now and ready today most likely.

12:00pm
The L6b FEB was mounted and the link was working fine. To fully test it we slide it in to be able to connect to the right detectors and it is still fine. Data cable not seated correctly might be the explanation. We didn't power any other FEB that share the same flange to see if that was an issue but given that other FEBs worked means we will take that risk. 
The plan is to extract these two boards and get them reworked. Then have all 10 FEBs and the octopus cleaned and mounted back on the cooling plate as soon as possible. Before sliding the cold plate in we would like to power all FEBs and walk through each one with a set of spare hybrids to make sure things are working.

1/16/2015

9:45am
Finished Ohming out the HV connections from the PS to the last REDEL connecting to the patch panel. No issue was found. What is left to do is to verify the GUI to physical hybrid mapping. This will be done once we have the patch panel attached.

2:45pm
Connected HV to the patch panel and mapped out the GUI to physical hybrid channel. This mapping was added to the DAQ & Power Mapping in Group C page. I will update the HV GUI with a physical hybrid ID (layer, hybrid channel instead of the existing mapping).

1/17/2015

1:00 pm - 5:00 pm

With all FEB's mounted on the support plate, the FEB's were powered up individually with the high speed cables connected.  All FEB's seem to power up fine, however, the DVDD current on FEB 5t and FEB 6t seem to indicate that there was no control link present.  These two FEB's were connected to the top two channels (0,1) of the 4th flange board using cable #10 and #11 respectively.  In order to check whether the problem was due to the FEB's or the cable/flange, a working flange board channel (flange board 3, channel 2, cable #6) was connected to FEB 5t and it was powered up again.  This time, a control link was established so the problem seems to be with either the cable or the flange board.  The same procedure was used to test FEB 6t and the results were the same, however, a different flange board and channel were used (see below).

Once a control link was established with all FEB's, they were tested to determine if they could sync all APV's connected to them.  This was done by using a stack of 4 L1-L3 hybrids connected to a single crossover board which in turn was connected to a single FEB.  The same stack of hybrids was cycled through all FEB's and only the FEB being tested was powered on.  As shown on the table below, only 5/10 FEB's were found to sync all 20 APV's.

FEB (ID)Flange Board/Channel/CableFPGA

DPM/Data Paths/APV's synced

Total APV's synced
1t1/0/220/0/5
0/1/5
0/2/5
1/1/5
20/20
2-3t2/0/454/0/3
4/2/4
5/0/5
12/20
4t4/2/991/3/5
3/3/5
5/3/5
6/2/5
20/20
5t3/2/662/2/5
3/0/5
3/1/5
3/2/5
20/20
6t4/2/991/3/5
3/3/5
5/3/5
6/2/5
20/20
1b1/2/102/2/5
3/0/5
3/1/5
15/20
2-3b2/2/331/3/5
5/3/5
6/3/5
15/20
4b3/0/880/0/5
0/1/5
0/2/5
1/0/5
20/20
5b3/1/771/1/5
1/2/5
2/0/5
15/20
6b3/2/662/2/5
3/0/5
3/2/5
15/20

The clock phases were not adjusted on those FEB's which couldn't sync all 20 APV's, so it's unclear if this would resolve the issue.

Equipment

Interlock board

see Group C interlock board for instructions on monitoring and controls.

Serial portserver

Digi Portserver TS 4: 192.168.1.217 on LAN. Telnet from ppa-pc91245, e.g. "telnet 192.168.1.217 2001" will connect you to port 2001. All serial ports are logged to /var/log/portserver on ppa-pc91245. Configure the portserver using its web interface or Telnet. Docs:  http://www.digi.com/support/productdetail?pid=1954

PortTelnet portHardwareUseful for
12001BK 1697 power supply, powering interlock boardresetting interlock board: SOUT000 to turn on, SOUT001 to turn off
22002iBootbar remote control power stripresetting TE chiller: login as admin:admin, "set output 1 off" "set output 1 on"
32003  
42004  

Thermoelectric chiller (backup chiller for FEB)

Oasis 190: manual

Error bits:

biterror
0Tank Level Low
1Tach Fail
2Thermistor Temp > Alarm
3PCW Low
4Thermistor Fault
5Pump Fault
6(not used)
7Thermistor Temp < Alarm

Procedures

Basic instructions to take a pedestal run with CODA

To be added.

 

 

Miscellaneous

Reloading PGP card drivers

Typically after a reboot we need to reload the pgp card driver. 

$ cd /u1/pgpcard/software/driver_old/

$ ./ pgpcard_load






 

OLD:Take a calibration run with expert SVT GUI

 

Start the DAQ:

 

$ cd /u1/software/software_new

 

$ source setup_env.csh

 

$ ./bin/frontEndTestGui

 

Click <read status> and make sure no error is seen. If so, check that the FEB is powered correctly.

 

Make sure the AxiXadc temperature is ok (50-60C).

 

Configure with config/FrontEndBoardConfigC01.xml

 

Click <read status> and check that more registers are found.

 

Turn on power to hybrids (see below)

 

Do a hard reset under commands/FebCore/HybridHardReset (current on AVDDP should drop ~100mA).

 

Click <Write config>.

 

Do a soft reset under commands/FebCore/HybridSoftReset.

 

Check that the hybrid currents measured are ok. Sync status for each channel can be seen in register RceCore/DataPath[x]/Synced, 1xf for powered channels.

 

Test Run SVT Group C Setup

 

Group C SVT test setup

 


 

  • No labels