Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  •  Documents:
    • Controls ESD - new language from Alex - Vincent to check

      "The MFX 6DOF Sample Table shall be controlled and integrated with  appropriate interlocks."

      "The MFX Detector Mover shall be controlled and integrated with  appropriate interlocks."

      everyone check
    • Vincent/ALex/Matt/Maggie update doc?
      • Maggie is following up
      • Vincent/Antonio/Rebecca - working on estimate for added scope. waiting for vendor (Cosilab) quote (maybe we will have this week)
    • Controls IRD in progress - maybe look at next time
    • Vac analysis R1 released - check naming convention
    • MFX + XPP mega schematic
      • Stand naming walkthrough
    • Laser PRD - revisit with new laser resources
      • Alan Mihanari
      • Patrick Kramer
    • ICD-Lasers - access on working site: https://slac.sharepoint.com/:w:/r/sites/lcls/lcls-2-he/wd/ICD/LCLS-II%20HE%20MFX%20Lasers%20ICD.docx?d=w73e52e9056f94e0cb9df481c8cd63f6d&csf=1&web=1&e=hJLtqF
      • Rebecca
    • ICD - controls - complete
    • RDS- R1
      • drawings added
    • Equipment anchoring BIO review - in process (Elena)
        • stands - complete
        • stopper
  • Controls Coordination - meet up to discuss status
    • Photon Stopper - controlled completely by BCS
    • timing system?
      • each hutch has an ATC crate
      • data structure is different for HE - working with data and detectors team
      • fast scope? or virtual?
    • Antonio working on XRT
    • XRT walk-though tomorrow
    • Enclosure Box selected  - 6Uish from Rittal
    • Controls subassemblies almost ready - starting to add enclosures along beamline
      transfocator controls - model and find space
    • Stand profiles - XRT, Hutch
    • Maggie and Vincent are POCs - maggie is out for a few weeks.
    • Rack Plan - next weekHardware is in mechanical scope- controllers in controls scopein good shape
    • out of scope items - older vac equipment, cameras, and motors etc. : how is this tracked?
  • Facilities
    • Meeting with Gerald on Thursday
    • Water Routing
      • regroup with F&O in January
      • add hardware to model
  • Detector Coord
    • Meeting on last Friday - Jana will attend to discuss documentation - single ICD for all hutches - individual IRDs
    • Walk through with Jana in FEH to look at space for CO2 chillers in Mezzanine (thurs)
      • space still needed while LCLS 1 is running.
  • Laser coordination
    • Add monthly meeting back to calendar
    • Engineer: Alan Mihanari, Scientist: Patrick Kramer
    • ICD/PRD/Laser ESD still in progress
      • transport line is now under raised floor — please verify height is correct.
        • stay-clears for in-between laser table and diagnostic stand - interface is tricky
          • LSS safety system shutters are there
          • controls need access- access from raised floor side?
        • Focus on PRD (working on CXI first)
        • Patrick touch base with Alex?
      • DxS-MFX transport line is still not finalized
        • but it is the preference
      • ATM config?
        • difference btwn L2Si vers and HE vers?
        Ongoing requirements negotiations/meetings
        • liquid phase chemistry stuff wasn't really captured → meeting on Monday with Tim VD/Roberto?
        • review of historical laser parameter requests
        • Tim was invited to last mtg. and explained his requirements
        • NO NEED FOR CHANGES. Written Agreement pending. (CC DF)
      • we are also ready to design laser out-coupling when laser team has details/requirements available
        • Does the detector situation matter? beam tube size? this geometry is important...
        • ideal hole diameter?
        • what is needed?
        • what is common ?
        • document on confluence and eventually in PRD
      • Resend Z location info to M. Greenberg - help him figure out divergence etc. which will let us know what hole diameter we need...
      • thermal issues (see below)
        • temp requirements?
        • current requirement in RDS: +/-0.5 deg C
        • better if laser outside of hutch?
    • Radiation safety
      • photon dump design kicks off this month
        • photon dump size for MFX
          • it wil be ~ 44cmx44cm
        • ESD in progress with mechanics specifiedneed a controls engineer (to complete prelim design of electronics and complete ESD)
      • ray trace
        • data input complete
        • walk through with RP during next meeting(s)
      • KB
        • chiller check - rack space - under diag1
        • check perimeter (for enclosure) - in model
        • Status?
      • IE