During this long shutdown, the setup for the vacuum and motion lines was almost completed (October 2022) in the FEE.  Panel B940-009-R17-DRL-01, B940-009-R17-DRL-02, B940-009-R17-DRL-03 and, B940-009-R17-DRL-04 were installed correctly on are now installed and grounded on the alcove, and the FEE device cables (GCC, GPI, VGCs ) were tested using the test boxes by Josue.

...

The devices will be shortly added to the PLC by Jyoti. All the long-run cables needed for the RP test have been properly pulled but not terminated due to a shortage of connectors.

Installation works will continue in hutch 1.1. Vacuum The vacuum panels and cables are almost ready to install for both, HRX and SRX, lines. The installation work will continue in the coming weeks in Hutch 1.1.

Soft-limit display issues

...