TXI installation for RP air attenuation test

Federica Murgia 

TXI will conduct RP testing on the HXR line in March - April 2023. This test is to verify air attenuation models at different repetition rates.

During this long shutdown, the setup for the vacuum and motion lines was almost completed (October 2022) in the FEE.  Panel B940-009-R17-DRL-01, B940-009-R17-DRL-02, B940-009-R17-DRL-03 and, B940-009-R17-DRL-04 were installed correctly on the alcove, and the FEE device cables (GCC, GPI, VGCs ) were tested using the test boxes by Josue.

DC panels and cables were installed in H1.1 in the middle of September.

The devices will be shortly added to the PLC by Jyoti. All the long-run cables needed for the RP test have been properly pulled but not terminated due to a shortage of connectors.

Installation works will continue in hutch 1.1. Vacuum panels and cables are almost ready to install for both, HRX and SRX, lines.

Soft-limit display issues

...