Margaret Ghaly Vincent Esposito 

Over the past couple of months, the ECS HE team has been making significant progress on the new controls infrastructure designs. The cost estimates for each hutch has been mostly completed and we are approaching PDR-level readiness in many areas. PDR is now planned for September 2022 (exact date TBD).

The team is working on refining the designs and continues to focus on the PDR, collaborating closely with the mech-E leads and Cosylab.

Mitch Cabrall has joined the effort and is working on Jama integration. <couple sentences about the upcoming Jama and usage>.

MEC-U Update

Jing Yin Alex Wallace 

...