HE Controls

Margaret Ghaly 


ECS presented XES controls design status for the February Director's review. The review focused on preparation for CD2/3 with focus on plan, design status and resource profile. The team demonstrated that as per December 2020 DOE Status review recommendation that lessons learned have been addressed and being implemented. 

The team also showed the plan and ramp up towards CD2/3 now that we have secured the resources needed to execute the project. The review committee observed in their reports that our designs appear to be sufficient at this point.  Currently, the team is focused on preparing for the upcoming DOE Review in MArch.

Controls ICD under review

...

Victor S. Elmir Omar Quijano 

QRIX

Margaret Ghaly 

Image Added

We have been busy with testing, checkouts and Install for QRIX endstation Controls. The schedule has been pulled forward with tasks that needs to be completed/ready in preparation for Toyama's visit to install and checkout the spectometer arm.

All the in vacuum stages have been functionally tested prior to installation. The qRIX Motion and Vacuum PLC are up and running with their IOCs and vacuum screen live.

Installation and termination of 80% of vacuum control components (DRLs and cables) are complete and 50% of motion controls components.



DC System Updates

Divya Kameswaran 

...