DateEventStatusResponsibleComments/Issues 
Thur, Jul 30thRequirement Slide Template for L2's Kurita, Lawrence

Create a first cut for the L2s - create template slide after Friday flowdown call (Kurita)

Add column in risk registry to identify "Key Driving" requirements. Have L2's and Charles pick up to 10

Send this to project on Friday after flowdown call reviews

 
Fri, Jul 31Send Requirement Slide Template for L2's Kurita, LawrenceReview with flowdown group and send to project 
Mon, Aug 3SE & Risk Slides for PD Kurita, AkeribSE summary slides; Risk Slides for PD and L2s, DRM meeting being scheduled 
Tue, Aug 4 Requirement Slides for L2s Kurita, Guarino, Besuner

Create a first cut for the L2s - create template slide after Friday flowdown call (Kurita)

 
on-goingPBD verification Kurita, LawrenceCharles, Nadine - Meeting being scheduled with detector group and J. Ruhl. Currently the PBD has not been validated by sims and is on-going. 
Tue, Aug 4 Risk Slides for L2s Kurita, Akerib

Option 1: Show top risks (maybe 5 or 7) with current assessment and "if mitigated" assessment. Since we don't have time to determine the appropriate risk strategy and what the project wants to fund to lower their risks, we can show them the process and the fact that we believe we can bring this project in successfully.

Option 2: Consider eliminating risk slides (most of the SE team did not think this was a good approach)

 
Tue, Aug 4ICD slides Grudzinski, Besuner

Bobby to designate each ICD with a maturity rating something like "outline-only" "most parameters identified not quantified" "many parameters quantified" or something along those lines (maybe just by numbers, less than one).  Then remove reviewer permissions on the less-mature ones and provide links in review presentations to more mature ones.  Analogous to the spotlight cost/schedule presentations on some of the more mature elements of the project.

Update to the block diagram for site (Wait until after review)

 
Tue, Aug 4Plenary Dry Run  SE to provide slides to management; requirements and risks 
Thu, Aug 6Breakout Dry Runs Kurita, Besuner

Minor updates. Will start with the Deliverable slides leading the reviewers to our "key" docs that are ready for review.

Do we need another dry run?

 
Fri, Aug 7Post Plenary Talks  SE to provide risk updates for Jim's talk. Anything else? 
Fri, Aug 7Post Breakout Talks Kurita  
Tue, Aug 11 (TBD)Review Support Documents Posted see CD-1 Deliverables  
Tue, Aug 4Key Deliverables Posted  SEMP, RMP, Risk Registry 
Tue, Aug 11 Supporting Docs  Add response to recommendations 
Tue, Aug 18Review Starts    

...