Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Schedule

also change energy to
Day/WeekDateActivities Program
Thursday-SaturdayDec/6-8T577 stand alone running. Day shift AMO beam unusable. 
SundayDec/9T577 running at 5 GeV 
MondayDec/10Day: T577 running at 3 changing energy to 8 GeV.  Night: T539 at 8 GeV 
TuesdayDec/11Day: T577 running at 8 GeV.  Night: T539 (TBC)at 8 GeV 
WednesdayDec/12Day: T577 changing to 3 GeV until beam off 1pm Beam off normally at 9am but may go until 1pm ? 

Main Goal

The Nov/2018 T539+T545 session had reduced beam time due to one primary LCLS experiment didn't permit the 5 Hz parasitic beam to ESTB. A makeup shared session was negotiated during this period with T577 (Moller calorimeter) also using secondary beam. The main goals  of this test session: 

...

  2) An independent examination of the L1A time distribution with the SLAC HSIO2+FEB readout. Data taken so far with YARR all exhibited a very broad distribution. 

Preparation

Caladium was moved into place at the start of T577 and remote driven to far wall with 1-2 inch clearance from beam line so that we can remote drive it back to beam line.

A97 had 1000e tuning from Timon on YARR during last period. Checked with RCE+FEB calibration looking OK

A97ThresholdsNoise map
YARRImage AddedImage Added
HSIO2+FEB  

  B53 had brief tests by Aleksandra before sent to SLAC

B53Thresholds

Noise map

YARRImage AddedImage Added
HSIO2+FEB  

Installation Inventory

  • RD53A module on DUT mounting frame
  • FEB board + 12V supply
  • DisplayPort cable
  • Agilent LV supply with GPIB controller, LV cable to FEB. Ethernet cable to Fanless box.
  • Keithley HV
  • TLU box with its voltage supply
  • Additional NIM discriminator from ESA for better trigger fanout cleanup + LEMO cables