10-Shared running with T577
Day/WeekDateActivitiesProgram
Thursday-SaturdayDec/6-8T577 stand alone running. Day shift AMO beam unusable. 
SundayDec/9Time early for possible first move of Caladium onto beamlineT577 running at 5 GeV 
Monday-Dec/10Day: T577 running at 3 GeV.  Night: T539 also change energy to 8 GeV 
TuesdayDec/11Day: T577 running at 8 GeV.  Night: T539 (TBC) 
WednesdayDec/12Unclear if beam can go beyond 9amBeam off normally at 9am but may go until 1pm ? 

Main Goal

The Nov/2018 T539+T545 session had reduced beam time due to one primary LCLS experiment didn't permit the 5 Hz parasitic beam to ESTB. A makeup shared session was negotiated during this period with T577 (Moller calorimeter) also using secondary beam. The main goals  of this test session: 

...

  2) An independent examination of the L1A time distribution with the SLAC HSIO2+FEB readout. Data taken so far with YARR all exhibited a very broad distribution. 

Preparation