DeliverableComplete DateResponsible
3 monthly reportsMonthly 15th, 31stRobert
Camera subsystem FDR, MRR site and document prepRoughly monthlyMark
Camera document control:
doc mgmt, prep, routing, release
(As needed, currently
4-10 hours per week)
Mark

LCLS-II, LCLS (0.1 FTE)

...