Item/TaskSub-item/taskOwnerDatesComment
FEB
 
Ben  
 layout 

done

 
 fabrication done 
 loading 9/3Received 8/29 
 testing 2 boards 9/512 
 rest of FE boards fab and loaded 9/1219 
 all FE boards tested 9/1926 
L4-6 Half-module production Tim/Omar  
 apv25 loading done 
 hybrid & sensor QA done 
 half-module production incl. QA 9/5 two modules to go on 9/2
L1-3 Module assembly Tim/Sho  
 Modules for detector  9/512 
 Spares 9/512 
L4-6 Module assembly Tim/Sho  
 Modules for detector 9/1219 
 Spares 9/1219 
FEB support Richard  
 Machine slots in support box  done 
 Design pockets (need final FE board)  9/12 
 Fabrication and dry assembly 9/1526 
Mechanical dry run assembly Who?  
 w/o cabling and real FEBs (but FEB cold plate) 9/5 first stage mech progressing well
     
Motion control system check Takashi/John  
 Test stages on vac box 9/5 Work with Matt on details
 Connect bottom U channel, set limits, calibrate 9/12conflict with survey? 
 Connect top U channel, set limits, calibrate 9/12 
Survey Tim/Sho overview and procedures needed
 L1-3 module survey 9/1219 
 L4-6 module survey 9/12919 
 U-channels survey 9/1926Need mounted modules (see below).
 SVT full assembly survey 9/22-9/26 Do after final assembly and checkoutCoordinate with alignment group (see below)
Internal cabling Tim/Dave  Critical Path–Push Hard
 Magnet wire signal transmission test done 
 Magnet wire high voltage test donePelle will do it. 
 FEB mezzanine card layout done 
 FEB mezzanine card fabrication 9/512 
 Hybrid mezzanine card layout 9/5done 
 Hybrid mezzanine card fabrication 9/512 
 L1-3 cross-over board design 9/125 
 L1-3 cross-over board layout 9/12 
 L1-3 cross-over board fabrication & assembly/checkout 9/12 19Push for 3 day turnaround.
 LV mezzanine card layout  9/5 
 LV mezzanine card fabrication  9/12 
 

HV mezzanine card layout

 done 
 HV mezzanine card fabrication done 
 Cable to LV (patch to FEB) 9/19Ben to get quote on connect SOON
 Cable to HV (patch to FEB) 9/19 
 prototype hybrid-FEB bundle assembly 9/1219Needs cards back and FEB 
 prototype cross over-FEB bundle assembly  9/26Needs cross over board 
 prototype bundle tests with FEB 9/1926 
 production bundle assembly and test 10/6critical path for full assembly (see below)
 FEB power bundle design (flange/patch) done 
 FEB power bundle assembly (flange/patch) 89/265Need cable length estimate. 2 days of shop work.
 FEB high voltage bundle design (flange/patch) done 
 FEB high voltage bundle assembly (flange/patch) 89/265Need cable length estimate. 2 days of shop work.
 

FEB data cable design (flange/FEB)

 done 
 FEB data bundle assembly (flange/FEB) done?9/5 
External cabling & Power pelle  
 High voltage 89/22122/3 bundles done. Waiting for more wire.
 Low voltage Done.9/19mod needed to present  bundle 
 Fibers Done.Between flange and DAQ crate.
 PS checkout Done. 
 PS epics control 910/56Can control through backup interface until ready.
Power flange Pelle  
 Flange w/ board assembly 9/12doneOne spare included.
 Testing with FEB and PS 9/12Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping 

Done.

 
 Board testing Done.Needs Ben for high-speed tests.
 Flange w/ board assembly 8/20-8/27done Potting.
 Board fabrication (spares) 9/526Spares, no rush. 
 Board loading (spares) 910/53 ditto
 Board testing (spares) 910/510dittoNeeds Ben for high-speed tests
Chiller and cooling system Marco9/12 
Target Clive/Marco  
 Design 9/5 
 Fabrication 9/19 
 Testing 9/26 
Wire frame holder Clive/Marco/Takashi  
 Design done 
 Fabrication 9/12Wire Stretching
 Testing 9/12  U-supports, FEB cold plate, stages 8/8 
  Define cable lengths for power and HV bundles  8/8 
Final SVT Assembly    
 Mount modules in U-channels and survey 9/2226 See survey above
 Dress modules in U-channels with cabling 910/26cabling not ready?10Use cables and cards completed 10/6
 Assemble FEBs on cooling plate and dress with cables 10/1710cables are ready 10/6  Need 11 days?
 Full SVT assembly including stagesand cabling 10/2217Ready for full system testing
ATCA/RCE Platform hardware Ryan/Pelle  
 RTM layout doneAfter testing trigger interface at JLab.
 RTM fabrication & loading done 
 RTM checkout 9/512 
SVT DAQ commissioning Ryan/Ben  
 Commissioning of RCE platform with multiple FEBs and hybrids

 9/8-9/19Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly.
 Commissioning/testing of full RCE platform 10/2013Use all final hardware with increasing number of FEBs/modules.
Shipping Pelle/Matt/Bob  
 SVT Box designDesign 89/295 Nr of boxes, isolator requirements for transport of delicate modules
 Procurement/fabrication SVT BoxesBob10/5 
 Assemble SVT BoxesBob10/12 
 Design Spares Boxes 9/12 
 Order standard boxesMarco9/26 
 Pack Boxes  9/19 
 AssemblyShip boxes 10/3