Item/Task | Owner | sub-item/task | Dates | Comment | ||
---|---|---|---|---|---|---|
FEB | Ben | |||||
layout | Done 8/4 | |||||
fabrication | 8/6-8/12 | |||||
loading | 8/13-8/20 | |||||
testing | 8/21- | |||||
L4-6 Half-module production | Tim | |||||
apv25 loading | 8/7 | |||||
hybrid & sensor QA | 8/12 | |||||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | ||||
L1-3 Module assembly | Tim | |||||
L4-6 Module assembly | Tim | |||||
Mechanical dry run assembly | Shawn | |||||
w/o cabling and real FEBs (but cold plate) | 8/8 | |||||
Motion control system check | Takashi | 8/15 | ||||
Survey | Tim/Takashi/John | overview and procedures needed | ||||
Modules | ||||||
U-channels | ||||||
SVT full assembly survey | ||||||
Internal cabling | Tim/Dave | |||||
Magnet wire signal transmission test | done | |||||
Magnet wire high voltage test | 8/8 | Pelle will do it. | ||||
FEB mezzanine card layout | 8/8 | |||||
FEB mezzanine card fabrication | 8/15 | |||||
Hybrid mezzanine card layout | 8/13 | |||||
Hybrid mezzanine card fabrication | 8/20 | |||||
pre-production bundle assembly | 8/21-8/26 | |||||
pre-production bundle test with FEB | 8/27-9/3 | |||||
production bundle assembly | 9/4-9/12 | |||||
FEB power bundle design | done | |||||
FEB power bundle fabrication | bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | |||
FEB high voltage bundle design | done | |||||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | ||||
External cabling & Power | Pelle | |||||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | ||||
Low voltage | Done. | |||||
PS checkout | Done. | |||||
PS epics control | 9/1 | Can control through backup interface until ready. | ||||
Power flange | Pelle | |||||
Fabrication | 8/8 | One spare included. | ||||
Testing with FEB and PS | 8/8 | Need dummy connector on power. High voltage with banana plugs? | ||||
Signal flange | Pelle | |||||
Fabrication | ||||||
Chiller and cooling system | ||||||
Target | Clive/Marco | |||||
Design | ||||||
Fabrication | ||||||
Testing | ||||||
14 12. target--design, fab, check 13. wires--design, fab, check 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes