Date | Events |
---|---|
5/5, 11am | Readiness meeting |
5/5, 4pm | Shutdown of fastcopy, L1, pipeline. Disable pipeline job submission from FASTCopy. Some web applications may stay up. |
5/5, 5pm | Remaining jobs drained out of batch farm. GLASTTREND in read-only. |
5/5, 6pm | GLASTTREND transfer (1a) should be be started by now |
5/5, 10pm | OPTIONAL: Once at least 600GB has been transferred, we might be able to start conversion of some GLASTTREND files. Not too likely to impact transfer performance, as it’s not likely to be hitting the same discs. |
5/6, 6am | Transfer of GLASTTREND should be completed. Notification that all applications will be down, including any that may have still been up after 6pm. Transfer of remaining databases (step 2a) on glast-oracle machines should commence. |
5/6, 10am | CONTINGENCY POINT: Should the transfer (1a), but NOT conversion (1b), of GLASTTREND exceed this time limit, then we shall ABORT step 2 entirely, and proceed ONLY with step 1. |
5/6, 2pm | The conversion of GLASTTREND (1b) must be more than half way finished, and the transfer of the remaining files (2a) must be more than halfway finished. If not, we need to decide on which to proceed with based on how far along they are. |
5/6, 3pm | The transfer of remaining files (2a) must be completed. The conversion of the files (2b) should be started. |
5/6, 5pm | The conversion GLASTTREND (1a) must be completed. The conversion of the files (2b) must be completed. GLAST_DP_TEST database must be up, and the schema migrations for the pipeline will be started. |
5/6, 7pm | The schema migrations should be finished. GLASTTREND, GLASTGEN, and other databases should be up. Applications should be started. |
...
In Stage 1, we will migrate the Trending data (GLASTTREND account). This involves the following:
Shutdown of fastcopy, L1, pipeline. Disabling of pipeline job submission from FASTCopy automation.
Let remaining jobs drained out of batch farm. GLASTTREND in read-only.
...