Hardware Proposal: PPA has requested $600k of annual hardware funding from DoE to cover small experiment and peak computing needs. This is primarily for cycles; storage needs seem modest.

FY13-14 Projection/update

Fermi

$600k Options include

  • coast on CY13 cluster nodes addition
  • replacing 2 Oracle servers
  • potentially another PB disk
  • unknown amount of tape (5 TB?)

FY13 Projection

Fermi

$600k Options include

  • replacing 2 Oracle servers
  • 35 nodes to go into the general queues
  • potentially another 400 TB disk
  • unknown amount of tape (5 TB?)

...

Anchor
midFY12
midFY12

Mid FY12 Update

Fermi

$500k left to spend in CY12. Options include

...

complete LTDA purchase - CD already knows the details. Retire old fileservers, using returned thumpers from Fermi.

...

Fermi

...

expect ~400 TB fileservers and 10 standalone linux servers. Presumably to be used for retiring old servers. 

...