  • we are trying to collect information about upcoming Fermi computing outages (disks, oracle, network) to improve planning
  • when planning an outage, please send an email to datalist and write the description here (including requested duration and preferred timeframe)
  • we will try to combine outages as much as possible, in order to maximize uptime for time-critical services (FASTCopy, pipeline, etc.)
  • once the plan is finalized, don't forget to send a message to glast-outage and the collaboration (if applicable)

Upcoming outage requests

Not yet scheduled (target date: late September or early October 2012)

  • NFS server change from old sulky machine(s) to wain031, affecting ISOC Ops: /u23, /u28, /u41, /u42. The selected method of making this cut-over will determine the nature and length of the outage. More details and discussion on the datalist email list.

...