Detailed description of switching to SCP control:
- Switch back to SCP control using remote switch (and later flip local switch
to MBCD mode).
- Stop ioc-li**-cv01 (switch back to alternate ports)
Leave sioc-sys0-cv01, sioc-sys0-cv02, sioc-sys0-cv03 running.
Boot sioc-li**-ky00 with non-test version
- Reconfigure gateway so that LI** PVs are again served by SLC.
- Verify that PDUs are working from SCP control, may need to reset PDUs from
SCP reboot LI** micro. IPL all LI** PIOPs from SCP.
- Verify that SCP control is restored and status is reading properly from EPICS
controls.
- Restart klystron CUD matlab process
- Set AIDA klystron service to SLC mode
- Restart MDL loop (need to add this to script)
- If backing out in LI20, HSTA ON LI20 PDU 3 and 4, then reboot LI20 micro