- Barry passed along a large, possibly too detailed flowchart via email (To be parsed / summarized...)
View file name MECU-LLNL-143 20231211 Experiment Model - Shot Sequence.pdf height 250 - Subsystems:
- NIF Collaboration Manager
- Target Area Collaboration Manager
- Bundle Collaboration Manager
- Bu35 Bundle Collaboration Manager
- Rough Sequence:
- Begin Shot
- Populate Plan
- Implement Plan
- Ready
- Sequential Rod Shot Pre-Countdown
- Sequential Rod Shot Countdown
- <<Rod Shot>>
- Sequential Rod Shot Post-Countdown
- Sequential Rod Shot Analyze Shot
- Ready
- System Shot Pre-Countdown
- System Shot Countdown
- << System Shot >>
- System Shot Post-Countdown
- Analyze System Shot
- End Shot Cycle
https://nifuserguide.llnl.gov/home/4-laser-system/41-laser-configuration