LSSTCAM charge numbers:16714-B2121, 10139 16713-B2019B2311

Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.

...

DeliverableComplete DateResponsibleBlockers/Issues
Write eTraveler assembly and test procedures for Camera Cryostat including refrigeration system.11/30/16Mark/Robert 
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use
5/16/16Mark/Robert
  • Standards complete, project to announce and socialize.
Write eTraveler procedures for CR wavefront sensor receipt, verification and shipment to SLAC6/10/16Mark

Input from Camera QA

eTraveler procedure for mechanical
assembly of raft electronics boards
(attach coldbars and FPGA heat sink)

Done 5/4/16

Robert 
eTraveler procedure for raft electronics
board initial testing (bring up board and
load firmware. Prep for TS-REB testing)

Complete 5/23

Robert 
Meet with Camera on what RGA snapshots to post for REB boards5/26Mark 
eTraveler procedure for posting RGA
results
Complete TBDMark/Robert

Coordination with Mark Bostic at SLAC for posting RGA
results

...

DeliverableComplete DateResponsibleBlockers/Issues
Finish release of 0266 ICD4/27Mark
  • Out for signoff (still)
Finish release of Platform ICD4/20Mark 
Finish release of Timing ICD5/4Mark
  • Talk to Matt Weaver and Boyes on some scope still
    floating around
Finish release of HPS FRSs5/11Mark
  • Waiting for direction from E-beam Controls
Finish release of HPS ESDs5/11Mark
  • Waiting for direction from E-beam Controls

...

DeliverableComplete DateResponsibleBlockers/issues
Summer intern - AIR Elx software library API docs, consider Doxygen   
Review permissions scheme for ppareg
Confluence space
 Mark 
Reorg and new navigation scheme for
ppareg Confluence spaec
 Mark 
Run interference with LCLS, LCLS-II doc
control and CDR/PDR/FDR and CD* review
prep.
 Mark