LSSTCAM charge numbers:16714-B2121, 10139 16713-B2019B2311

Other upcoming tasks/issues coordinated with Nadine Kurita for LSST Camera can be found here Camera Documentation Planning.

...

DeliverableComplete DateResponsibleBlockers/Issues
Write eTraveler assembly and test procedures for Camera Cryostat including refrigeration system.11/30/16Mark/Robert 
eTraveler standards, conventions,
best practices documentation. All Camera
subsystems must use
5/16/16Mark/Robert
  • Standards complete, project to announce and socialize.
Write eTraveler procedures for CR wavefront sensor receipt, verification and shipment to SLAC56/2710/16Mark

Input from Camera

CR team

QA

eTraveler procedure for mechanical
assembly of raft electronics boards
(attach coldbars and FPGA heat sink)

Done 5/4/16

Robert 
eTraveler procedure for raft electronics
board initial testing (bring up board and
load firmware. Prep for TS-REB testing)

Complete 5/23

Robert 
Meet with Camera on what RGA snapshots to post for REB boards5/26Mark 
eTraveler procedure for posting RGA
results
Complete TBDMark/Robert

Coordination with Mark Bostic at SLAC for posting RGA
results

...

 
DeliverableComplete DateResponsibleBlockers/IssuesDevelop ePix100 "advanced user" doc
for LCLS-II: full register documentation of readout
system and ASICs; describe known detector
edge cases behavior and configurations
TBDMark
Finish release of 0266 ICD4/27Mark
  • Out for signoff (still)
Finish release of Platform ICD4/20MarkOut for approval according to Matt 
Finish release of Timing ICD5/4Mark
  • Talk to Matt Weaver and Boyes on some scope still
    floating around
Finish release of HPS FRSs5/11Mark
  • Get blessing from Matt Boyes on outline/contentsWaiting for direction from E-beam Controls
Finish release of HPS ESDs5/11Mark
  • Get blessing from Matt Boyes on outline/contentsWaiting for direction from E-beam Controls

ePix (0.1 FTE)

Charge numbers:

...

DeliverableComplete DateResponsibleBlockers/issues
Develop ePix100 "advanced user" doc
for LCLS-II: full register documentation of readout
system and ASICs; describe known detector
edge cases behavior and configurations
TBDMark 
ePix100A detector data sheet5/13Mark 
  • Done, needs only proofread before sending out
ePix100A installation guide5/13Mark 
  • Done, needs only proofread before sending out
ePix100A detector ops/api guide5/13Mark
  • Talk to Gabriel about # of runs for dark
    frames, gain maps, single-photon experimentsWaiting for some sections from Gabriel on calibration use cases

TID-AIR General Work (??? FTE)

...

DeliverableComplete DateResponsibleBlockers/issues
Summer intern - AIR Elx software library API docs, consider Doxygen   
Review permissions scheme for ppareg
Confluence space
 Mark 
Reorg and new navigation scheme for
ppareg Confluence spaec
 Mark 
Run interference with LCLS, LCLS-II doc
control and CDR/PDR/FDR and CD* review
prep.
 Mark