Reviewed FAC recommendations and wrote notes for all entries.
Some were transferred from Jing to Alex so that he can address them at the DR.
Barry and Nate's input is needed for cosylab effort estimates. Alex will present efforts and estimates for cosylab at DR.
Steven reviewed his recommendations and did not find any that overlap with controls.
Worry List
We did not review worry list since we are doing this at the technical integration meetings.
P6
Steven had some confusion on laser design scope in 1.04, but we clarified that it was for laser integration. Jing will get this adjusted in the next release.