Time | Item | Who | Notes |
---|
30 min | Status | All | - ePixM Phase III was approved at PEC on Friday, re-planned to deliver working prototype for downselect vs. VFCCD in late 2020.
- 1 in-air ePixBig (Jan 2020) and 4 thick-Si MEC (May 2020) quads also approved. Need a kickoff meeting and probably a little more hands-on than first article(?)
- Peter Denes visiting tomorrow to discuss SXR imager requirements:
- 50um pixel pitch
- 15e- rms read noise
- 5kHz frame rate or greater
- 512x512-class pixel format, to be tileable to 1Mp-class with >90% fill factor. Buildup from smaller 4-side buttable modules is acceptable.
- 1000 photon well capacity @
1.5keV 530eV - >
90% 70% QE at 277-1.5keV - High Vacuum compatible (10e-9T)
- Compatible with 2m electronics cabling and cooling hoses to allow in-chamber articulation.
- Compact packaging for mounting within q-RIXS vacuum chamber (dimensions to be specified, but like iVFCCD concept))
-
Visible-blind to laser pump background.
- Decide ASC electrical after move-in costs known
- Rebar scan complete, anchors set(?)....set up ASC coordination meeting (KZ)?
- Status JF 4M effort. 4pm meeting
today.... - Update > Status RIXS-CCD test planning
- Masks not here yet, checking with Sallie.
- Ground issues resolved from first test?
- Late March slips to mid-April??
- Do first test at SSRL to decouple from ASC sked??
- MEC EMP testing CSPAD/ePix Date TBD
- PH gone first week April
- KN Wave8 upgrade for FIM CDR Mid-April
- ePix10k requires new MPODS, working issue
- Laser SoP moving forward...set up so no laser glasses necessary...administrative controls OK
- eGun interlock doc (2wk.)
- Lost cabinets were not delivered....(2wks)
- KZ: Control room furniture install this afternoon.
- Vacuum equipment moving today w/techs.
- Riggers set for Thursday 10am.
- Status documentation/procedures effort
- How many fibers do we have to run to B84?? Work with Jana to tell Mark Foster (2wk)
|
5 min | Budget Update | mmck | - ASC: $191k spent, $62k remains
- Ops: $233k spent, $925k remains (Feb Actuals, incl. I&D, detector research, mgmt.), $28k under plan
|
15 min | Review ASC First Projects | all | Coordinate/update lab schedule |
10 min | Any other business | | |