******* June 5th, Thursday, update from Stepan
Dear all,
I am happy to inform that HPS chicane magnets are now installed in the
Hall-B downstream alcove.
Many thanks to the Hall-B engineering-technical team for the excellent
work. Great work!
Best, Stepan
Chicane magnets installed 5 June 14.JPG
*******June 4th, Wednesday, update from Stepan "Spectrometer magnet installed"
...
- Installation and Survey Homework - John (see attachment of draft)
- ASAD Draft - Stepan
ECal Installation and Survey - Raphael
...