- FEE Commissioning: December 1st?
- TMO first light (easier): Jan. 24, 2023
- KPP: MUST have ability to read out the piranha line camera on FZP and ability to read out two HSD channels on MBES but only if GMD/XGMD measurement doesn't work; could also be an opal
- RIX first light (harder): ~March 2023
- LCLS-II KPP test with soft-x-ray in the hxr line in txi (March/April) they may need a wave8 or a hsd or a (controls?) camera to see the signal? (phil heimann is coordinating) - air attenuation tests; 3 keV
- KPP measurements on hard x-ray line in the FEE (may only need power meter, or slow signal that gets fed back to ACR)
General to do
- recabling to srcf (cpo+ric+others)
- use data volume to each node to figure out cabling
- what should go through the bos? exclude opals?
- what should use MPO (Nov 1 checkpoint for laser locker/XPP; switch on Nov 16; revert by Nov 18 if unsuccessful) including BLD, IOC, FIM, XTCAV, Mono Enc TPR (we can switch daq timing independently of controls timing)
- IOC depends on Kukhee's software
- high rate BLD depends on Dawood's software
- Jeremy Mock writes about XTCAV: "Hi Chris, we can test the camera triggering soon, probably in October some time. However, I think XTCAV proper (the klystron) won't run on lcls2 timing until sometime next year. I think I heard maybe February...?". Pat Krejick is coordinating the change.
- 33kHz BLD: ebeam, gmd, test asap. waiting for software development (depends on Dawood)
- test reception of 33kHz gmd without beam ASAP working with Marcio
- commission s3df
- migrate ctl nodes (move hsd processes onto daq-tmo-hsd-01 (Ric), but not mono encoder)
- commission xpm0 in 208 (weaver)
- (would be nice) xtcav "nice" for acr? how do we share between tmo/rix: need bos-switchable timing?
- (would be nice) test psana2 live mode again (mona)
- training for scientists (e.g. on timing system and sequences) (matt)
- check we have psana2 detector interface for "sequence bits" (Matt thinks we have this: 272 bits)
- timing in all detectors
s3df to-do
...
- (done) psana1 (mikhail, valerio) psana2 (mikhail, mona, valerio)
- (done) smalldata code (silke, vincent)
- will ask wilko to move some psana1 data over
- need path to install packages
- done by early february?
- movers (wilko)
- few days of work. still needs some work on feb. 15
- need some kafka work for movers and elog (wilko)
- should be ready for early february. still needs some work on feb. 15
- need some data management machines and irods (replaced by rucio in a few months) integration (wilko)
- still needs some work on feb. 15
- data storage (omar)?
- backend spinning-disk (aka "s3") 10's of PB done early january
- will get 1.5PB of flash free space by third of week of january
- serious issue (has been worked-around by using "/home" and relaxing ACLs for FFB): no extended ACL's since mounted via nfs. need multi-cluster feature? (expected in april?) or fully functional nfs?
- could workaround by making group the expt group, but then access via ps-data (e.g. silke) wouldn't work
- mon-node mount of calibdir (under /sdf/data/lcls) via weka-nfs (IT) (done)
- will try third week of january
- ARP (murali, wilko)
- should be straightforward copy of what we currently have. confirm with murali. (still needs work on feb. 15)
- jupyter/ondemand (wilko, riccardo) (done)
- could provide yee with default kernels (cpo will contact yee/wilko)
- can run in batch queues (charged) and interactive nodes (free!!!)
- (done) LCLS group permissions syncing (wilko)
- finalize high-priority analysis mechanism (preemption? reservations?reservations, we believe)
- need coact (like iris at nersc) stuff from murali available by beginning of february
- need management accounts to create per-account CPU allocations with coact. still needs work on feb. 15
- will also coact to enable their s3df account
- need coact (like iris at nersc) stuff from murali available by beginning of february
- enable user access to s3df (IT)
tmo to-do
Equipment list:
- magnetic bottle (few hsd channels)
- 2 opals (fzp, atm). atm alignment could be in controls? eventually cvmi opal in run 22.
- 2 piranha (atm, fzp)
- bld (ebeam, gmd, xgmd)
...
Code Block |
---|
[camera, need by date, retire date] [cvmi_opal_1, oct 27, nov 19] - retire date is negotiable, (maybe needs to be earlier?) [cvmi_opal_2, oct 27, nov 19] - retire date is negotiable, (maybe needs to be earlier?) [atm_opal, oct 27, possibly run 22] [fzp_opal, oct 27, possibly run 22] [atm_pirhana, oct 27, not planned] [fzp_pirhana, oct 27, not planned] |
rix to-do
Equipment list:
- 3 andor newton
- 3 wave8
- 1 piranha (atm)
- 1 opal (atm)
- bld (ebeam, gmd, xgmd)
- high-rate interpolated mono encoder (caf)
- what is the right way to use that encoder (absolute or relative for the motor?)
- relative encoder is still with vendor; early next year arrival at SLAC; try to integrate and read out at higher rates (work with Zach)
- EXS Manta (coordinate with controls for timing/sequencing)
- 1 channel HSD for coarse timing (rate? 1 kHz ok if we can see the whole waveform)
...