Attendance:
Presentation:
Bhavna's investigation on crosstalk
https://docs.google.com/presentation/d/17j36x4jc_ISrbj3n1EXLRPRLZQtEXgt1ILh9TvQtwKg/edit?usp=sharing
Zongde's page on beamtime linearity study
https://confluence.slac.stanford.edu/x/aI0tGg
Agenda/Notes:
- ePixM June 15th Beamtime Prep:
June15th beamtime: V2 vs V4 modules? What measurements do we want?- Setup deployment on Wednesday, June 12, 9 am - 12 pm
- Confirmed by Matt Hayes
- Check detector running in DAQ
- Check the fibers connection
- Hardware Prep
- Fiber convertor and thined unit at ASC now
- New power cable ordered by Dawood
- Pinhole holder design
- Need to optimize and prevent light leakage. (Chris Koerber)
- Measurement plan
- Setup deployment on Wednesday, June 12, 9 am - 12 pm
- Stuff to do:
- Look at crosstalk with softHI, look for Y, improve fitting
- mini-X tests in marrietta
- Status
- softHI and auto:
- attenuator scan, but sit at one point for a long time (for more stats). How long?? Zoom in on low flux range.
- softHI pinhole re-do: something odd with the data from day1.
- location dependence of
- effect (Different pinhole position?)
- take data that simulates a potential correction algorithm (black out part of the detector
- softHI pinhole re-do: something odd with the data from day1.
- )
- make measurement plan sheet before next meeting (Zongde)
- Schedule the staffing;
- next week meeting (Zongde)
- Setting up the pre-setup meeting (include TID)
- Stuff to do:
- Look at crosstalk with softHI
Run 909 (Soft/Hi), (slice 10/10) (Xavier's plot on slack)
- mini-X tests in marrietta
- Status
- Look at crosstalk with softHI
- Basic script suite for beamtime
- Git training?