DR Preparation | DR Template - What are the 5-6 high level steps that are needed to get you to CD-2/3? P6 tasks too detailed
- Cost and Schedule Dashboard - Traci will provide
- Annotate and use red banner to give high level message
- Cost comparison - Traci will provide
- Explain changes. "TBD" area will be corrected by Traci.
- One-pager
- If System is on critical path, presenter should address
- CD-3A Long Lead Procurements have been identified (HE-LP). Remainder of procurements are after CD-2/3.
- Risk table - Karl Flick will provide. Additional Monte Carlo slides will be provided by Charles.
- New Challenges Resulting from Notional Funding Profile
- Include Deliverability Issues as a direct result of flat funding profile
- Include mitigation issues to address each issue
- Items Yet to be Addressed
- Recommendations from Prior Reviews
- Laser folks to meet offline to discuss how to present
- Show the examples most pertinent to charge questions
Sandboxing - Team will prioritize Worry List, go through list and develop mitigations.
- Date TBD. Week after next.
|