- LAT-12x (Science Modes)
- Eric indicated that this must be completed no later than 9/25 (P Hart)
- Window for execution on the LAT is 9/25-28
- LAT-20x (Science Performance Diagnostics)
- Additional configurations in E2E csv file
- Completed
- LAT-23x (GRB Handling)
- Update needed to use new functionality provided by FSW B0-7-0
- Philip estimates it's a couple of days of work
- Eric points out this script will be eclipsed by a test to interact with the spacecraft and the GBM, so it is lower priority to get this done
- Neil says that perhaps the FQT is adequtate to demonstrate the FSW functionality
- The most important task here is to develop a plan for the Observatory-level test, then provide to / coordinate with Chip Meegan (GBM at MSFC) to agree on details
- LAT-90x (File system dump)
- Needs to be run prior to LAT EGSE shipment to SASS (9/12)
- R Baun to supply details
Tools for generating configurations (E Grove)
...
- There is a lot of work to do in 3 weeks
- Not listed above: Bent Pipe ramifications, lots of outstanding JIRAs
- Push for getting new Analysis Engine and Data Ingest deployed by 10/1
- Get LAT-12x done by 10/19/25
- Get LAT-90x done by 9/9
- Build MOOT support into next release of LICOS and some scripts
- Deploy the Ancillary Tracking tool based on a solid Ancillary area snapshot
- Get a release of LICOS, et al. deployed by the time of the FSW B0.7.0 upload
- Decide on configuration tools plan