Agenda

  • FSW update repercussions on LICOS, et al.
  • New Analysis Engine deployment
  • MOOT deployment
    • Possibly: Further MOOT development
  • Management of Ancillary area
  • Test scripts: new and updates
  • Schedules
  • AOB

Attending

J Bogart, R Claus (chair), K Fouts, E Grove, P Hart, N Johnson, B Lee, J Panetta, J Thayer, S Tuvi

Summary

FSW (J Thayer)

  • Build B0-7-0 is targeted for 9/15
    • Major change affecting LICOS et al. is mnemonic changes
  • Planning 2 days of regression testing
  • Planning a week of test bed time for testing with LICOS scripts
    • Mostly involves intSEApp
    • Also power On/Off scripts are affected
  • Most changes are already in the prod branch in AFS
  • Upload to LAT is planned for 9/25, followed by regression testing on the LAT through 9/28
    • Needs to be coordinated with LICOS, et al. releases
    • Goal: Make beta release of LICOS, et al. by 9/15

New Scripts

  • LAT-12x (Science Modes)
    • Eric indicated that this must be completed no later than 9/25 (P Hart)
    • Window for execution on the LAT is 9/25-28
  • LAT-20x (Science Performance Diagnostics)
    • Additional configurations in E2E csv file
    • Completed
  • LAT-23x (GRB Handling)
    • Update needed to use new functionality provided by FSW B0-7-0
    • Philip estimates it's a couple of days of work
    • Eric points out this script will be eclipsed by a test to interact with the spacecraft and the GBM, so it is lower priority to get this done
    • Neil says that perhaps the FQT is adequtate to demonstrate the FSW functionality
    • The most important task here is to develop a plan for the Observatory-level test, then provide to / coordinate with Chip Meegan (GBM at MSFC) to agree on details
  • LAT-90x (File system dump)
    • Needs to be run prior to LAT EGSE shipment to SASS (9/12)
    • R Baun to supply details

Tools for generating configurations (E Grove)

  • Joanne is working on tools related to this
    • Won't be ready on the one month time scale
  • Byron has been working such tools as well
    • Tool is meant to be used to populate MOOT
    • It generates configurations from scratch
    • He could return to working on this after the bent pipe work is done
    • Limited amount of time: he'll be leaving GLAST at the end of this month
    • So far only CAL, ACD and Trigger are supported
  • Need to set up a brainstorming session to define what we want
    • Interface - How to interact with the tool(s)
    • Nomenclature for the intent of a configuration
  • Post meeting discussion with Jim and Selim:
    • Jim has started work on a tool chain that reads a LATc base config file and outputs a LATc config file, recalculating broadcasts
    • Could add folding in of 'delta' config files to change things like the bad channel list
    • This tool would address modifying existing LATc configurations
    • It avoids the time consumming LATTE based approach Lester set up
    • Jim agreed to write a note in Confluence describing the tools and how a user interacts with them

New Analysis Engine (P Hart)

  • Key change is the new version runs on datagram (LSF) files instead of LDF files
  • System is robust against dropped datagrams
  • System automatically processes new data files and retires them if the analysis script ran successfully
  • Updated GUI showing node running the analysis and the elapsed time
  • System is working with the exception of for the TkrNoiseAndGain and TkrTotGain scripts
    • TkrNoiseAndGain takes too long (24 hrs) and runs out of memory
    • TkrTotGain has a JIRA open against it LS-108 (also Jim says LCS-117 is still an issue)
  • Philip would like help to verify script outputs

Data Ingest

  • Current version sometimes drops datagrams (LCS-197)
  • Bryson says similar function used for Offline is not appropriate for Online
  • DataIngest is not suseptible to COM-64
  • Ric has volunteered to look into this

MOOT (J Panetta)

  • Jim has code base mostly ready for LICOS
  • Need to import config files into MOOT
  • Need to figure out how to label things and codify intent
    • Eric says that a small number of runs should cover most of the space
    • Eric agreed to make a list to help get this process started
  • See "Tools for generating configurations" above
  • Jim to work on integrating latest MOOT release into LICOS
    • Goal is to include this in the next LICOS release
    • Will update a couple of scripts to use MOOT

Ancillary Tracking DB tool (B Lee)

  • Tool is ready
  • Need a good, solid Ancillary area snapshot to populate the database
    • Only CAL writes a pedestal file during the CPT, else Ancillary isn't modified by CPTs
  • Pick up the snapshot during shipment of the LAT (between pre- and post-ship CPTs)
  • Eric says we'll want to recalibrate after TVAC
  • Need to carefully coordinate taking the snapshot in order to not get confused by running different configurations for pre- and post-ship tests

Conclusions

  • There is a lot of work to do in 3 weeks
    • Not listed above: Bent Pipe ramifications, lots of outstanding JIRAs
  • Push for getting new Analysis Engine and Data Ingest deployed by 10/1
  • Get LAT-12x done by 9/25
  • Get LAT-90x done by 9/9
  • Build MOOT support into next release of LICOS and some scripts
  • Deploy the Ancillary Tracking tool based on a solid Ancillary area snapshot
  • Get a release of LICOS, et al. deployed by the time of the FSW B0.7.0 upload
  • Decide on configuration tools plan