Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Osier, Ted O. 

Fong, Anthony Yun-ming

Reagan, Brendan

Cutino, Phil 

Justin Galbraith

Ashray Patel

...

Robert Plummer

Cavern Evaluation

TopicsNotes
Charge and Responses

Presentation by Brice Arnold.  

Kai recommends verbiage to be "FES Scope minus the Explicitly Designed Upgrades" (see Chapter 11, Section 11.2) https://slac.sharepoint.com/sites/pub/Publications/Forms/Legacy%20View.aspx?FilterField1=Document%5Fx0020%5FType&FilterValue1=Design%20Reports&FilterType1=Lookup&viewid=7b0b6c13%2D0334%2D46f5%2D8367%2Db2ff3505631f&id=%2Fsites%2Fpub%2FPublications%2FMECU%2DDR%2D0003%2Epdf&parent=%2Fsites%2Fpub%2FPublications

TAX

Major conflicts involve beam transport in TAX.  Note that not all conflicts have been resolved.  Recommendation is to descope or enlarge cavern size.

Deferred scope shall not be precluded.

Increased TAX height is included in 60% DGPS scope.

RRL and HE

Considered alternate beam dump approach.

Brice, Corey and Ted are managing master integrated model.

Need more offline discussion on Laser Hall - alignment lasers, diagnostic package.

What is the impact of precluding Delphi B?  Justin Galbraith:  Plan is the same, but height decreases.

Smaller magnification assumed but not in scope.  Implementation of any technical changes must go through TCCB.  Impacts Target Chamber PDR.  Any other technical assumptions?  Baseline long pulse?  Which expansion ration should be used - decision needed.  Michael Greenberg points out that larger beam size resulted in residual spatial chirp.  Needs offline discussion.

Controls System

Racks in progress of being updated in model, cable tray will have an impact.

Schedule

Technically limited schedule is not reasonable.  Credible decision needs all technical impacts.  Changes to cavern, even larger, will have impacts.