What | When | Resource Uptime Needed |
---|---|---|
vibe/acoustic |
| |
TVAC | Aug-Sept (40 days) | up to 8 hr outages allowed |
Kennedy Ops |
|
|
ISOC testing - Pre-launch
What | When | Resource Uptime Needed |
---|---|---|
ETE3 | August 2007 (2 days) | uptime needed |
ETE4 | Oct 2007 (2 days) | uptime needed |
ETE5 |
| uptime needed |
ETE6 |
| uptime needed |
ISOC Ops Sim 1 | Oct 2007 (about 4 days) | uptime needed |
ISOC Ops Sim 2 | Dec 2007 (about 4 days) | uptime needed |
Flight Operations Post Launch
...