- Announcements
- EPICS repository and build tree status (Wesley)
- Scaler waveform ROOT readout status (Hovanes)
- Status of the chiller cooling system document (Marco)
- Ongoing work on chiller controls (Wesley)
- SVT time line discussion (Takashi)
- Feb2 - ship to jlab (beginning)
- Feb 9 - reassemble in EEL and check (beginning)
- Feb 23 - Install in the hall.
- Manpower plan for the preparation and for the running in spring.
- Other items