Date

Action

0105/13

SLAC booth #303 (20' x 40' ) approved by SC11 management

03/29

Go ahead for SC11 planning

04/04

Kickoff meeting

04/29

2nd planning meeting

07/01

3D hardware type decided (3D monitor vs rear projection system)

07/13

Conference validation request submitted

07/15

Booth design complete

07/20

3D monitor selected

23

Pre-Planning meeting

06/01

Protein model prototypes ordered

06/05

Conference validation done

06/18

Protein model prototypes ready

06/21

Protein model selected

06/27

All Hands meeting

07/16 08/03

Start preparing DOE conference approval request

08/0301

Freeman order process begins

08/0801

SCinet connection order opens 3D monitor purchase order ready

08/03

Booth design complete

08/10

Booth theme Giveaways decided

08/22 Frames ordered15

3D printing of protein model starts

08/2528

Booth logo design readytheme decided

08/29

SCinet connection order opens

31

Artwork for shirts ready

08/31 09/01

Dell shirts ordered

09/0704

Print material ordered Handouts decided

09/0904

Additional display elements ordered DOE conference approval request submitted

09/1405

Artwork for handouts giveaways ready

09/1507

Giveaways ordered

09/10

DOE conference approval request submitted 3D monitor delivered

09/1614

Entry in Exhibitor Directory  Listing

09/14

Booth logo design ready

09/21

Handouts ordered Hanging sign printed

09/2928

Deadline for SCinet connection order to avoid $1000 late fee

0910/3001

Additional frame elements  Frames delivered

10/0318

Advance rate deadline for electrical connections

10/06
01

Shipping crates ordered

10/07

Giveaways  delivered Deadline for hotel cancelation without penalty

10/11
08

Display wall content ready LSST Hologram shipped to SLAC

10/1408

Protein model printed LSST Hologram delivered

10/1410

Frame material for hanging sign deliveredDeadline for hotel cancellation without penalty

10/1415

3D content ready

10/1415

Shipping list completed

10/17
15

Protein model assembled Deadline for early registration

10/18

Crate for hanging sign delivered

10/21

Handouts  delivered

10/27

Discount Deadline to Order all Freeman Labor, Furnishings & Services

1110/0219

Last day for advance shipments and Hanging Signs to arrive at Warehouse

Deadline for early registration

10/19

Shipping crates delivered

10/22

Display  pre-assembly completed

10/30

Posters printed

10/30 11/03

Packing hardware starts

11/0602

Packing hardware complete

11/0705

Hardware ready to be shipped by YRC

11/1008

Direct-to-site shipment arrives

11/1008

Exhibits Installation    8 am – 5 pm

11/1209

Exhibits Installation    8 am – 5 pm

11/1310

Exhibits Installation    8 am – 5 pm

11/1411

Exhibits Installation    8 am – 5 pm

11/12

Booth Cleanup            8 am – 4 pm

11/12

Exhibition Opening Gala 7 - 9 pm

11/13 15

Exhibition Open          10am – 6 pm

11/1614

Exhibition Open          10am – 6 pm

11/1715

Exhibition Open          10am – 3 pm

11/1715

Exhibits Dismantling  4pm 3pm Midnightmidnight

11/1816

Exhibits Dismantling  8am – 3 pmnoon

11/1816

Booth hardware shipped back to SLAC

12/01

Ship back LSST Hologram

12/17

Booth hardware distributed/recycled/disposed

 

 

...