Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 4.0
Gotchas - things to watch out for

...

1. Remember to reset/re-initialize the PDUs after switching a sector without IPL or reboot

2. Remember to reboot soft klystron ioc to get CAS

3. Remember to set SECTSBST PV to "NO" for any klystron that does not use the shared subbooster

 

SW Test Plan: Switch LI20-LI30 CAMAC to EPICS

1. Description/Purpose:

After the LCLS accelerator has been turned on and
checked out and tuned up using the SLC control system, we would like to begin switching the
sectors back to EPICS control to test and if all goes well, leave them in EPICS
control.

We would like to do this in 3 installments:

...

C. If B goes well, 2 or more days later, switch over remaining sectors. 3 hourshour

2. Systems Affected:

SCP Control of Sectors 20-30 Klystrons and other CAMAC
devices

3. Beam Required:

Yes, and klystrons active on the beam

4. Invasive:

Yes

5. Test time needed:

9 hours distributed over 3 separate days

6. Dependencies:

None

7. When:

Week of May 16 or later

8. Test plan:

(Pre-test) save SCP configs to restore afer test is complete.

...

d. If testing in LI20, HSTA OFF LI20 PDU 3 and 4, then reboot LI20 micro

e. Restart MDL loop (need to add this to script) 

f. Test!

g. If leaving a sector in EPICS control, enable alarms for that sector's CAMAC IOC. 

10. Backout plan:

a. For each sector, go to lclshome > LI**/Network > More CAMAC... >
Switch to SCP Control

Detailed description of switching to SCP control:

  • Switch back to SCP control using remote switch (and later flip local switch
    to MBCD mode).
  • Stop ioc-li**-cv01 (switch back to alternate ports)

Leave sioc-sys0-cv01, sioc-sys0-cv02, sioc-sys0-cv03 running.

Boot sioc-li**-ky00 with non-test version

  • Reconfigure gateway so that LI** PVs are again served by SLC.
  • Verify that PDUs are working from SCP control, may need to reset PDUs from
    SCP reboot LI** micro. IPL all LI** PIOPs from SCP.
  • Verify that SCP control is restored and status is reading properly from EPICS
    controls.
  • Restart klystron CUD matlab process
  • Set AIDA klystron service to SLC mode
  • Restart MDL loop (need to add this to script)
  • If backing out in LI20, HSTA ON LI20 PDU 3 and 4, then reboot LI20 micro