Migration from the old server to new server, 10g to 11g

Distilled Steps (Estimated 30 work days to completion, 6 calendar weeks)

  1. Take outage, Migrate pipeline and datacat dev database to new server
  2. Test out new server on Pipeline-II 1.4
  3. Test changes on new Pipeline-II 1.5 branch
  4. Take outage, perform pipeline and datacat prod TEST migration
  5. Test out temporary trending database, L1Proc at scale
  6. After Pipeline/datacat prod migration TEST, schedule actual migration
  7. Run migrated production pipeline on temporary trending table space for a few days
  8. After the trending database is migrated to the new server, update it with temporary trending values
  9. Swap to permanent trending database

Test migration of GLAST_DP_TEST tablespace (pipeline and datacatalog tables)

...