P106 Reprocessing

status: In Progress Indefinite HOLD
last update: 11 13 May 2010

This page is a record of the configuration for the P106 reprocessing project. It targets 200 runs of L&EO data for processing with a new alignment and other improvements to investigate issues with the Pass7 classification.

...

  • 11 May 2010 - Prepare task
  • 13 May 2010 - four test streams submitted...formally successful. Anders has given cursory glance at first few events of first stream (recon/merit only) and the log file, saying all looks okay. However, it has been discovered that the alignment issue thought to be an issue with the L&EO data is a non-issue. So put this task ON HOLD.

Configuration

The configuration for this reprocessing is nearly the same as for the ordinary science data with three exceptions: the run list was provided by Anders (and consists of a discontiguous set of runs); fewer data products are produced; and, the algorithm for finding FT2 files was modified to accommodate these earlier data (in fact, Warren produced a new set of 1-second FT2 files specifically for this reprocessing project). Note that the original list of runs counted 200, but a single run proved troublesome, 238781852, and was removed from the list, leaving 199 runs to reprocess.

...

ROOT version

v5.20.00-gl5

Skimmer version

v7r3p3-gl2

Timing

processClump (~23k evts) - about 53 CPU min (hequ), and 85 CPU min on fell

mergeClumps (full run) - about 62 CPU min (hequ), mostly due to gtdiffrsp

P106-LEO-FT1

Status chronology

...