  1. Floor survey for 2.5" embedment: DONE. OK.
  2. Clean machine and computer as well as possible: DONE.
  3. Installation:
    • to be done in July.
    DONE (July)
    #*
  4. Calibration: Jim has contacted the companyCalibration (already paid for).
3- Wirebonder: Installation DONE

...

  1. Wider variety of gloves:
    • Ask Tim/Chris
  2. Larger shoe covers: Jim is taking care of it.DONE.
    #*
  3. Glove dispenser for inside room:
    • Jim is taking care of it.
  4. More dispensers in gowning area:
    • Jim is taking care of it

...

  1. Buy tools:
    • Jim is taking care of it, with help from Chris for special tools.