  1. Floor survey for 2.5" embedment:
    • Jim is following up
  2. Clean machine and computer.
  3. Installation.
  4. Calibration (already paid for).
3- Wirebonder:

...

Installation DONE
4- Probe station:
  1. Fabricate anodized aluminium plate:
    • Jim is taking care of it. Plate expected within a few months.
  2. Transfer hood to new plate; replace fabric with rubber flaps (neoprene?).
    • need new plate.
  3. Need rack or table to hold test equipment.
    • to do: have to figure out what is needed: inputs from  Chris and Ryan.
  4. Clean.
  5. Install.

...