Procedure for use (alignment, operation)
~8/2 Thursday: documentation, pictures,...
8/3 Friday: iAT testing day
8/5 Monday: iAT work morning, Eric measures stuff in the afternoon
8/6 Tuesday: removal of SPL/LPL swap in the morning, ePix10ks IN and waterline connection in the afternoon (Ariel)
8/7 Wednesday: cabling of motors and DAQ (Peregrine)
8/8 Thursday: shot and EMP test (Eric, Philip H, DK, HJL)
8/9 Friday: shot and EMP test (Eric, Philip H, DK, HJL)
8/12 Monday: disconnect lines....removal of LPL/SPL setup in the afternoon (Ariel)
8/13 Tuesday: Users come
8/29 Thusday: Commissioning