  • ePixM June 15th Beamtime Summary:
    • Beamtime observation
      • mask design 
      • ePixM1 FPGA stopped working after changing the mask, power cycle. 
      • Swap the FPGA with ePixM2 unit from TID, we can talk to the detector but not working normally.
    • initial data analysis
    • ePixM hardware issue
      • One detector with bad readout board (original detector)
      • One detector with bad data coming from carrier board 
  • Action Items:
    • Determine what caused the detectors to fail.
    • Fabricate another engineering module to keep testing over the summer.