measurement schedule:

Beamtime ePixHR Feb 16/17 2024 - v2.xlsx

Shift scheduling:


Feb 16Feb 17
shift 1 (6p-1a)Philip, Dionisio, Kaz, LorenzoBhavna, Philip, Julian, Bojan
shift 2 (11p-6a)Bhavna, Zongde, Julian, Bojan, Dionisio (tentative)Kaz, Zongde


Lorenzo presentation and links:

...

  • Philip brought up that descrambling appears to not put the detector in the correct position. Dionisio has requested multi asic hardware for properly debugging this.
  • Lorenzo presentation:
    • We should run at 2.6V, it improved the linearity (both v1 and v2 has been updated to supply 2.6V to the ASIC now);

Action itemsTo Do: