Facility | Carrier | RF Interlock RTM | Digital Debug RTM | Down Converter | Up Converter | Required Delivery Date |
---|---|---|---|---|---|---|
Phase Cavity |
|
| 1 | 1 x rev A01 (Installed) 1 x rev A01 (Installed) 1 x rev A03 (Installed) 1 x rev A03 | 1 x rev A01 (Installed) 1 x rev A01 (Installed) 1 x rev A03 (Installed) 1 x rev A03 | Digital Debug RTM x1, Downconverter rev A03 x1, Upconverter rev A03 x1 by 9/25/2023 expected: 9/27/23-Stephen Currently reworking boards |
Laser Locker |
|
|
|
|
| All delivered |
XTCAV | 3 | 3 x rev A01 | 3 x rev A01 | (Expecting RF Interlock RTM x1 is already delivered to Thuy) Upconverter rev A01 x3, Downconverter rev A01 x 3 Delivered 10/17/23 | ||
STCAV | 1 | 1 | 1 x rev A01 | 1 x rev A01 | Carrier x1 & RF Interlock RTM x1 is already delivered to Thuy Upconverter rev A01 x1, Downconverter rev A01 x1 by 10/4/2023Nov. 2023 Downtime | |
LINAC LLRF Position 26-3 | 1 | 1 |
| 1 x rev A01 | 1 x rev A01 | All delivered |
...