The LCLS-II-HE controlsteam continue to advance designs for the various instrument areas. CXI instrument PDR review was conducted April 19th. FXT, FEE and XRT Transport, Engineering Peer Review has also been conducted April 28th. The team is awaiting the committee's report from those two reviews in order to address any recommendation and move forward into the next activity. Common Components EPR targeted for mid to late May. The team also finalized the BCR for Lasers with the XES lasers scope changes.
MEC-U Controls has slowly begun ramping up in March and April and will begin to shift focus to laser beam transport controls and infrastructure design. Some notable MEC-U topics from the past couple months can be found below.
...